Difference between revisions of "Atomic Threats In The Baltic Sea Region/Working meetings/Fourth meeting/Ostrovets"
From Nuclear Heritage
Jump to navigationJump to search (Created page with "{{Atomic Threats In The Baltic Sea Region}} '''<= 4th project working meeting''' ''presentation ...") |
m |
||
Line 5: | Line 5: | ||
''presentation provided from Belarusian anti-nuclear organizer:'' | ''presentation provided from Belarusian anti-nuclear organizer:'' | ||
− | == Belarus antinuclear | + | == Belarus antinuclear campaign == |
* '''NPP construction in Belarus''' - started in Ostrovetsky district of Grodno region 2009 | * '''NPP construction in Belarus''' - started in Ostrovetsky district of Grodno region 2009 | ||
* The works on NPP infrastructure construction (roads, communications ets.) started summer 2009 before: | * The works on NPP infrastructure construction (roads, communications ets.) started summer 2009 before: |
Revision as of 19:36, 11 May 2014
Project Atomic Threats In The Baltic Sea Region - call out - timeline - book - Nuclear Baltic Map
media group - planning meeting - working meetings - updating internet conferences - coordination - finances
<= 4th project working meeting
presentation provided from Belarusian anti-nuclear organizer:
Belarus antinuclear campaign
- NPP construction in Belarus - started in Ostrovetsky district of Grodno region 2009
- The works on NPP infrastructure construction (roads, communications ets.) started summer 2009 before:
- EIA procedures by Aarhus and Espoo were even started,
- the project was developed and license issued.
- Facilities for NPP construction (mini-plant for concrete production) were finished by summer 2011 before the project were done and license issued.
- 1st reactor building construction was started 31 May 2012 - 6 month before the project description was finished and more than 1 year before the license was issued.
- Belarus antinuclear campaign, Ecohome